- Today
- Holidays
- Birthdays
- Reminders
- Cities
- Atlanta
- Austin
- Baltimore
- Berwyn
- Beverly Hills
- Birmingham
- Boston
- Brooklyn
- Buffalo
- Charlotte
- Chicago
- Cincinnati
- Cleveland
- Columbus
- Dallas
- Denver
- Detroit
- Fort Worth
- Houston
- Indianapolis
- Knoxville
- Las Vegas
- Los Angeles
- Louisville
- Madison
- Memphis
- Miami
- Milwaukee
- Minneapolis
- Nashville
- New Orleans
- New York
- Omaha
- Orlando
- Philadelphia
- Phoenix
- Pittsburgh
- Portland
- Raleigh
- Richmond
- Rutherford
- Sacramento
- Salt Lake City
- San Antonio
- San Diego
- San Francisco
- San Jose
- Seattle
- Tampa
- Tucson
- Washington
Newton Today
By the People, for the People
Newton's Aurora Heights Elementary School Renovation On Track
Project expected to wrap up by end of July as planned
Apr. 4, 2026 at 2:57pm
Got story updates? Submit your updates here. ›
Newton school administrators overseeing the renovation and expansion of Aurora Heights Elementary School say the construction work is progressing on schedule, with drywall, plumbing, electrical, and window installation all underway. The $12.9 million project is slated for completion by the end of July.
Why it matters
The Aurora Heights Elementary renovation is a major investment in the Newton school district's infrastructure, upgrading aging facilities and expanding capacity to serve the growing community. Keeping the project on time and on budget is crucial for minimizing disruption to students and staff.
The details
Key progress includes drywall and mudding in the renovation areas, plumbing rough-ins for the new addition, passing the electrical inspection for the addition, and window installation. New LED lighting and boilers have also been installed throughout the building.
- The Newton School Board approved the construction documents on September 23, 2024.
- The $12.9 million construction contract was awarded to Graphite Construction Group in Des Moines.
- The project is expected to be completed by the end of July 2026.
The players
Tom Messinger
Newton School Superintendent overseeing the Aurora Heights Elementary project.
Graphite Construction Group
The Des Moines-based construction firm awarded the $12.9 million contract for the Aurora Heights Elementary renovation and expansion.
What they’re saying
“Drywall and mud are going up in the renovation areas. Classroom plumbing rough-ins are going in at the new addition. The in-wall electrical inspection was passed for the new addition, and window installation is underway in the new addition as well.”
— Tom Messinger, Newton School Superintendent
What’s next
The Newton School Board will receive another update on the Aurora Heights Elementary project at their next meeting.
The takeaway
By keeping the $12.9 million Aurora Heights Elementary renovation on schedule, the Newton school district is ensuring minimal disruption to students and staff while upgrading aging facilities to serve the growing community.