- Today
- Holidays
- Birthdays
- Reminders
- Cities
- Atlanta
- Austin
- Baltimore
- Berwyn
- Beverly Hills
- Birmingham
- Boston
- Brooklyn
- Buffalo
- Charlotte
- Chicago
- Cincinnati
- Cleveland
- Columbus
- Dallas
- Denver
- Detroit
- Fort Worth
- Houston
- Indianapolis
- Knoxville
- Las Vegas
- Los Angeles
- Louisville
- Madison
- Memphis
- Miami
- Milwaukee
- Minneapolis
- Nashville
- New Orleans
- New York
- Omaha
- Orlando
- Philadelphia
- Phoenix
- Pittsburgh
- Portland
- Raleigh
- Richmond
- Rutherford
- Sacramento
- Salt Lake City
- San Antonio
- San Diego
- San Francisco
- San Jose
- Seattle
- Tampa
- Tucson
- Washington
El Paso Electric Proposes New McCloud Natural Gas Plant
The utility plans to present details on the facility tied to the Meta data center development.
Mar. 31, 2026 at 10:36pm
Got story updates? Submit your updates here. ›
El Paso Electric is expected to give a presentation on Wednesday about a proposed new natural gas-generation center called the McCloud facility in Northeast El Paso. The utility says the center would provide constant, round-the-clock service for customers at a higher capacity, and that Meta will pay for the project. El Paso City Council is set to discuss the proposal on Wednesday.
Why it matters
The new McCloud facility is tied to the growing Meta data center development in Northeast El Paso, which requires a reliable and high-capacity energy source. This project represents El Paso Electric's efforts to meet the energy needs of major corporate clients while potentially reducing water usage compared to other generation methods.
The details
El Paso Electric is proposing to build the new McCloud natural gas-generation facility near the Meta data center development in Northeast El Paso. The utility says the center would provide constant, round-the-clock service for customers at a higher capacity than existing infrastructure. El Paso Electric also claims the facility will not need to use water, and that Meta will pay for the project's construction.
- El Paso Electric is expected to present details on the McCloud facility proposal on Wednesday, March 31, 2026.
- El Paso City Council is set to discuss the proposal on Wednesday, March 31, 2026.
The players
El Paso Electric
A regional electric utility serving customers in West Texas and southern New Mexico.
Meta
The parent company of Facebook, which is developing a major data center in Northeast El Paso.
El Paso City Council
The governing body of the City of El Paso, which will discuss the McCloud facility proposal.
What’s next
El Paso City Council is set to discuss the McCloud facility proposal on Wednesday, March 31, 2026, which will determine the next steps in the project's approval process.
The takeaway
This project represents El Paso Electric's efforts to meet the growing energy demands of major corporate clients like Meta, while potentially reducing water usage compared to other generation methods. The outcome of the City Council discussion will be crucial in determining if the McCloud facility moves forward.