- Today
- Holidays
- Birthdays
- Reminders
- Cities
- Atlanta
- Austin
- Baltimore
- Berwyn
- Beverly Hills
- Birmingham
- Boston
- Brooklyn
- Buffalo
- Charlotte
- Chicago
- Cincinnati
- Cleveland
- Columbus
- Dallas
- Denver
- Detroit
- Fort Worth
- Houston
- Indianapolis
- Knoxville
- Las Vegas
- Los Angeles
- Louisville
- Madison
- Memphis
- Miami
- Milwaukee
- Minneapolis
- Nashville
- New Orleans
- New York
- Omaha
- Orlando
- Philadelphia
- Phoenix
- Pittsburgh
- Portland
- Raleigh
- Richmond
- Rutherford
- Sacramento
- Salt Lake City
- San Antonio
- San Diego
- San Francisco
- San Jose
- Seattle
- Tampa
- Tucson
- Washington
Minnkota Says $110M Data Center Power Project Won't Affect Customers
The cost of the powerline and substation needed by a data center north of Fargo has risen from $75 million to $110 million.
Apr. 2, 2026 at 7:39pm
Got story updates? Submit your updates here. ›
The technical components powering a new data center project north of Fargo represent a major infrastructure investment in the region.Fargo TodayThe cost of the powerline and substation needed by a data center north of Fargo has risen from $75 million to $110 million, but developers say the data center company will still cover the entire cost of the project. Applied Digital needs the project to power its data center being built between Fargo and Harwood, which requires 280 megawatts of power at peak demand.
Why it matters
The data center project is a major investment in the region's infrastructure, but the rising costs could have implications for the project's timeline and profitability. However, Minnkota has assured that the increased costs will not be passed on to its customers.
The details
Applied Digital will pay for the project upfront, but it will be owned by Minnkota Power Cooperative. The project includes a substation east of Interstate 29 near the data center and a 345-kilowatt powerline connecting to existing powerlines. Minnkota is hoping to start construction later this month and have the line operating in the fall, but it still needs Public Service Commission approval. The approximately 45% increase in the project cost is related to trying to meet the fall deadline, the scarcity of materials, and tariffs.
- Minnkota is hoping to start construction later this month.
- Minnkota is aiming to have the powerline operating in the fall of 2026.
The players
Minnkota Power Cooperative
A regional electric cooperative that will own the powerline and substation project to serve the data center.
Applied Digital
The data center company that will pay for the entire $110 million project upfront.
Cass County Electric
A member of the Minnkota co-op family that will deliver power to the data center.
North Dakota Public Service Commission
The regulatory body that needs to approve the project before construction can begin.
What they’re saying
“Minnkota's large load customer, Applied Digital, would pay for the project upfront with no 'cost shift' to customers of Cass County Electric, which will deliver power to the data center.”
— Brendan Kennelly, Minnkota Chief Operating Officer
What’s next
The North Dakota Public Service Commission needs to approve the project before Minnkota can begin construction later this month.
The takeaway
Despite the rising costs, the data center project remains a significant investment in the region's infrastructure that will be fully funded by the data center company, ensuring no additional costs are passed on to Minnkota's customers. The project's timeline is still on track, pending regulatory approval.
Fargo top stories
Fargo events
Apr. 3, 2026
Fargo Force v Tri-City StormApr. 4, 2026
Fargo Force v Tri-City Storm



